Work in Progress

Roadwork ahead sign
Library photo

Some projects/roadworks may take a bit longer than anticipated to complete due to extended periods of rain, or contractors being unavailable. Current capital improvement projects are listed here. Other minor capital projects may also be underway.

Choose the suburb or area to see all work being undertaken in that area:

  • In the wake of the recent floods, Council is working through assessing all reports of damage to assets. Depending on the extent of the damage, work will range from minor repairs which can be completed quickly to major works involving design and construction to build resilience into infrastructure. Staff are working alongside a team of consulting engineers to assess and prioritise work as the recovery phase begins.  Stay informed on progress in the updates below.

    Updates Flood Impacted Locations
  • Location: Shire Wide
    Project details:

    Council will soon commence traffic counting at various road intersections across the Shire, 

    Traffic counting is an important activity in Council's infrastructure planning. It provides valuation information on the flow of traffic, evaluates road performance, and enables Council to make informed decisions about the design and operations of our infrastructure network for the future.

    Start date:  Multiple days commencing March 2023. See the project news for dates and locations
    Related document:
    Location: Multiple locations - grading
    Project details:

    Maintenance grading activities on local gravel roads will commence shortly. Roads will be inspected prior to the start of work and maintenance carried out in sections based on required grading treatment. Grading is conducted to repair potholes, corrugations and to improve drainage, improving our road networks for all users.

    Roads being graded as part of this program are included in the Project News.

    Start date: July 2022
    Related document:

     

  • Location: Black Mountain Road Landslide
    Project:

    If you would like to be kept up to date with this project please download the Let's Keep in Touch document and email to mail@noosa.qld.gov.au.

    See the Black Mountain Road page for all the latest information.

    Location: Black Mountain Range Road
    Project:

    Contractors will soon commence road resurfacing work on Black Mountain Range Road.

    Residents are asked to avoid parking on the street.

    Start date: 7 August 2023
    Duration: 11 August 2023, weather permitting
    Related documents:

     

  • There are no capital projects underway at this time.

     

  • There are no capital projects underway at this time.

  • Location: Schreibers Road
    Project: Work is set to commence to repair damaged infrastructure as a result of the 2022 flood event on Schreibers Road Cooran.
    Start date: 24 September 2023
    Related documents:

    For further information please visit the Disaster Recovery 2022 Floods page

     

  •   Currently no capital projects underway.
  • Location: Musa Vale Road
    Project:

    Designs and tender documentation are being prepared to reconstruct the road edge on the single-lane section of Musa Vale Road, Cooroy. This section of road was damaged during a landslip caused by the major flooding event in February/March 2022.

    The next steps of the project include:

    • design revision
    • design concept submission for QRA funding approval
    • final design development
    • invitation to tender
    • reconstruction of road asset.

    An update on the planned construction date will be provided when more definite information is available after the development of the final design.

    Related document:
    Location: Olivine Street
    Project:

    Contractors will soon commence road resurfacing work on Olivine Street Cooroy. 

    Start date: 18 October, 2023
    Duration: 3 nights, subject to weather and construction conditions
    Related documents:

     

  • There are no capital projects underway at this time.

  • There are no capital projects underway at this time.

  • Location:  
    Project:

    There are no capital projects underway at this time.

     

  • Location: Middle Creek Road
    Project:

    Road works to improve safety will soon take place on Middle Creek Road, Federal between Federal State School and Andersons Road.

     Works will include:

    • widening and sealing of road shoulders to 6 metres
    • lime stabilisation of subgrade
    • regrading of table drains
    • line marking and signage improvements.

    Middle Creek Road will remain open for the duration of works and traffic control will be in place where required.

    Start date: 9 January 2023
    Duration: Three months, subject to favourable weather, contractor and product availability
    Related document:

     

  • Project: Pender Creek Road
    Project details:

    Maintenance grading and drainage activities continue on local roads with grading work to be carried out on Pender Creek Road, Kin Kin to prepare for a new road surface and improved drainage to be installed in the coming weeks.

    Start date: 23 June 2023
    Related document:

     

     

     

  • There are no capital projects underway at this time.

  • Location: Noosa Parade
    Project:

    Contractors will be undertaking vegetation pruning and the replacement of street trees along Noosa Parade, from the Garth Prowd Bridge to the Munna Point Bridge next week.

    This work will be carried out as part of the Noosa Parade Corridor Upgrade to replace vegetation that has perished during the on-maintenance period, or any vandalism damage that may have occurred.

    Start date: Monday, 21 August 2023
    Duration: 1 week, weather permitting
    Related documents:
    Location: Arkana Drive
    Project:

    Council contractors will shortly start work on construction of a retaining wall in the median strip of Arkana Drive, Noosa Heads.

    the new retaining wall, approximately 130m long and 1.1m high, will be constructed out of grouted rock and will replace the existing timber structure.

    Start date: Mid August 2023
    Duration: 8 weeks, weather and construction conditions permitting
    Related documents:
    Location: Noosa Spit
    Project:

    Following monitoring of the progress of the nourishment works, Noosa Council in conjunction with the Contractor, have made the difficult decision to halt work on the sand nourishment work at Doggie Beach. It was decided to stop the dredging work due to the challenging nature of that section of the Noosa River and the likelihood of it not being completed before the permit deadline of late September.

    The decision has been made to prevent further disruption to beach and river users. This means the beach and adjacent waterway will be reopened to the public.

    Under the permit, work can only be conducted during April to September to minimise environmental impacts such as the seasonal migratory shorebirds. Council will continue to investigate options to complete the sand nourishment work when possible.

  • There are no capital projects underway at this time.

  • Location: Noosa Waters Lock & Weir
    Project details:

    Stage 3, construction of the Noosa Waters Lock and Weir renewal will commence on Tuesday, 3 October. Work is expected to be complete by Monday, 13 November 2023.

    During the work boating vessels will be unable to transit between the Noosa River entry canal and the estate canals. Residents wishing to utilise their boating vessels on the Noosa River during this time are encouraged to make other arrangements for trailer their vessels if possible.

    Start date: 3 October 2023
    Duration: Completion by Monday, 13 November 2023 subject to contractor, material availability and weather
    Related document:
    Location: Eenie Creek Road
    Project details:

    Contractors will soon commence road resurfacing work on Eenie Creek Road, Noosaville.

    Start date: 11 October 2023
    Duration: 3 nights, subject to weather and construction conditions
    Related document:

     

  • Location: Peregian Skate Park
    Project overview:

    Skateboard and scooter riding are popular family activities for all ages in the Noosa Shire. To meet demand, Council will shortly commence an upgrade of the popular Peregian Beach Skate Park.

    Council has been working closely with an experienced skate park designer, Concrete Skate parks to come up with a design that not only satisfies the needs of users, but also suits the unique footprint of the site.

    The procurement process for construction is beginning.

    Start date: Construction is expected to commence during winter 2023
    Related document:
    Location: David Low Way
    Project overview:

    Contractors will soon commence road resurfacing work on David Low Way Peregian Beach from Peregian Esplanade to the Heron Street roundabout.

    Work will be undertaken at night between the hours of 6.30pm and 6.30am.

    Heron Street will be closed between 6.30pm and 6.30am with detours in place.

    Start date: Sunday, 7 May 2023
    Duration: Completion expected by Friday, 19 May 2023, weather permitting
    Related document:

     

     

  •  

    Location Station Street
     Project details:

    Contractors will soon commence kerb and asphalting works on Station Street, Pomona.

    Kerb works will take place during the day between 6.30am and 6.30pm, and road resurfacing will be completed at night between the hours of 6.30pm to 6.30am.

    Start date: Wednesday, 27 September 2023
    Duration: Till 13 October 2023, subject to favourable weather and construction conditions.
    Related document:
    Location Stan Topper Park
    Project details:

    Council contractors will shortly start work on pathway construction in Stan Topper Park, Pomona.

    Start dates:

    5 June 2023

    Duration: Two (2) weeks, weather permitting
    Related documents:
    Location Mt Cooroora car park
     Project details:

    Contractors are returning to the Mt Cooroora car park to complete some identified defect work.

    The car park will be temporarily closed from Monday, 15 May for approximately 3 weeks, weather permitting.

    Start date: Monday, 15 May 2023
    Duration: 3 weeks subject to favourable weather and construction conditions
    Related document:
    Location Stan Topper Park
    Project details:

    Council contractors will shortly start work on pathway construction in Stan Topper Park, Pomona.

    Start dates:

    5 June 2023

    Duration: Two (2) weeks, weather permitting
    Related documents:

     

  • Location: Sobraon Street
    Project:

    Following the intense rainfall event over the weekend of 26-27 February, damage to the constructed stormwater outfall protection occurred. This has impacted a small section of the sandy slope near the Sobraon and Vernon Street, Sunrise Beach intersection.

    Temporary protection work will involve the blocking of three upstream stormwater inlets and the installation of a surface protection to the outfall to manage damaging stormwater flow. As a result, road users may experience additional flow along the roadway of Sobraon Street during periods of heavy rainfall.

    Related document:
    Location: Tingira Crescent
    Project:

    Council staff will soon commence work to replace the existing post and rail fence on Tingira Crescent, Sunrise Beach.

    Approximately 70 metres of fence will be replaced from south of the Chalet Lookout.

    Start date: Tuesday, 21 March 2023
    Duration: 3 days, subject to weather and construction conditions
    Related document:

     

  • Location: Beach Access 32 and 35
    Project details:

    Work will shortly commence for renewal maintenance works to Beach Access 32 and 35 at Sunshine Beach and improve safety for pedestrians.


    Detour routes will be marked for alternate beach access via Beach Accesses 31 and 33 while work is carried out.

    Start date:

    Beach Access 32 will be closed from 3 July to 28 July 2023

    Beach Access 35 will be closed from late July to late August 2023

    Related document:
  • There are no capital projects underway at this time.

  • Location:

    Butler Street
    Project details:

    Contractors will soon commence road resurfacing work in Butler Street Tewantin.

    Night works will be undertaken to reduce the impact on traffic. Work will be undertaken between the hours of 6.30pm and 6.30am.

    Start date: Sunday, 13 August 2023
    Duration: Friday, 18 August 2023
    Related document:
    Location: Werin Street
    Project:

    Council will shortly start work on replacing a damaged culvert at the southern end of Werin Street, Tewantin.

    The work will reduce erosion and improve slope stability.

    Start date: 31 July 2023
    Duration: 2 weeks, weather permitting
    Related document:

     

  • There are no capital projects underway at this time.

  • Location: Upper Pinbarren Creek Road
      No capital projects at this time.