Location: Hilton Esplanade - Living Foreshore Pilot Project
Project: Upcoming works along Hilton Esplanade will combine routine foreshore nourishment with a small-scale Foreshore Protection Pilot Project. Sand will be dredged from areas of the Noosa River and placed on selected sections of the foreshore to replenish sand lost through natural coastal processes, including tidal currents, wind waves and boat wake. These routine works help maintain the foreshore and support its ongoing resilience.
Foreshore nourishment works are expected to commence in September 2026.
Related Documents:
Location: Doonella Lake Bridge
UPDATE 2 Nov 26: A full road closure will be required overnight from 9pm on Thursday, 5 November, until 5.00am on Friday, 6 November 2026 , weather permitting. During this time, the bridge will be fully closed to all vehicle traffic, with no vehicle access available across the bridge. Pedestrians and cyclists will continue to be able to access the adjacent pedestrian bridge throughout the works.
Project: We're upgrading Doonella Lake Bridge for a safer, stronger connection. Originally constructed in 1968, the bridge plays a critical role in our local transport network, connecting Tewantin and Noosaville and carrying an average of over 20,000 vehicles daily, along with many pedestrians and cyclists. These essential works will improve the bridge’s safety, durability, and accessibility for all road users.
Duration: Set to commence in July 2026, with work expected to finish by mid December 2026, subject to weather and construction conditions.
Related document: Project News(PDF, 522KB)
Location: Outlook Drive -Asphalt Reseal Works
Project: Contractors will soon commence asphalt resealing works on Outlook Drive to renew the road surface, improve driving conditions and extend the life of the pavement.
Duration: Work is scheduled to commence on Wednesday, 14 October 2026 with completion expected by Friday, 16 October 2026, subject to weather, contractor availability and site conditions.
3/11/2026 Update: Scheduled to commence on 17th November (weather permitting).
Related Document: Works Notice(PDF, 251KB)
Location: Stringybark Court - Kerb and Channel Works
Council staff will soon commence kerb and channel works on Stringybark Court, Tewantin. Work will include kerb and channel replacement link up to new stormwater pit.
Duration: Work is scheduled to commence on Tuesday, 10 November 2026 with completion expected by Friday, 13 November 2026, subject to weather and site conditions. The work will be undertaken during the day between the hours of 6.30am and 6.30pm.
Related document: Works Notice(PDF, 217KB)
Location: Poinciana Avenue - Asphalt Heavy Patching Works
Contractors will soon commence asphalt heavy patching work on Poinciana Avenue in Tewantin.
Work is scheduled to commence on the 1st October 2026 with completion expected by the 2nd of October 2026, subject to weather, contractor availability and site conditions. The work will be undertaken at night between the hours of 6.30pm and 6.30am.
3/11/2026 Update: Completion date still to be confirmed due to weather delays.
Related document: Works Notice(PDF, 260KB)
Location: John Street - Kerb and Channel Works
Contractors will soon commence Kerb and Channel works on John Street, Tewantin. Work will include renewal of defective kerb and channel.
UPDATED 13/10/2026: Works will commence on Monday, 16th November and completion Friday, 27th November.
Related documents: Works Notice(PDF, 191KB)
Location: Tewantin Splash Park - N19 Amenities Maintenance
Contractors will soon commence repairs on the Tewantin Splash Park amenities at Doonella St, Tewantin. Work will include the replacement of doors and linings to the cubicles.
Work is scheduled to commence on Monday, 26 October 2026 with completion expected by Friday, 30 October 2026, subject to weather, contractor availability and site conditions.
Related documents: Works Notice(PDF, 233KB)
Location: Werin Street - Pathway Repair Works
Council staff will soon commence pavement repair works on Werin Street Tewantin. Work will include removal of defective footpath panel and replacement.
Duration of work: Work is scheduled to commence on Thursday, 12 November 2026 with completion expected by Tuesday, 17 November 2026, subject to weather and site conditions.
Related Documents: Works Notice(PDF, 216KB)
Location: RSL Memorial Park - Playground Shade Sail and Renewal Works
Contractors will soon commence playground renewal works on RSL Memorial Park, Tewantin.
Work will include removal of existing soft fall around the swings, spring toys and base of the slides, and the installation of new Play Matta attenuation surfacing and the installation of the new shade sail.
Duration of work
Shade Sail work is scheduled to commence on Monday, 9 November 2026 with completion expected by Monday, 9 November 2026, subject to weather, contractor availability and site conditions. 09/11/2026 Update - Due to contractor availability, the installation of the RSL Memorial Playground shade sail has been postponed to late November. A further update will be provided once dates are confirmed. Thank you for your patience. Related Documents: Works notice(PDF, 180KB)
Renewal work is scheduled to commence on Monday, 16 November 2026 with completion expected by Friday, 20 November 2026, subject to weather, contractor availability and site conditions. Related Documents: Works notice(PDF, 180KB)