Work in Progress

Roadwork ahead sign
Library photo

Some projects/roadworks may take a bit longer than anticipated to complete due to extended periods of rain, or contractors being unavailable. Current capital improvement projects are listed here. Other minor capital projects may also be underway.

Choose the suburb or area to see all work being undertaken in that area:

  • Location: Shire Wide
    Project: Noosa Council is currently implementing multiple pathway upgrades throughout the Noosa Shire as part of its pathway renewals program. Since February, contractors have successfully completed renewal works at five sites, with an additional four scheduled for completion in the coming months. In total, thirteen sites across the Noosa Shire are scheduled for renewal by June 2024.
    Start date: March / April 2024
    Related documents:

    For further information please visit the Disaster Recovery 2022 Floods page

  • Location: Black Mountain Road Landslide
    Project:

    If you would like to be kept up to date with this project please download the Let's Keep in Touch document and email to mail@noosa.qld.gov.au.

    See the Black Mountain Road page for all the latest information.

    Location: Cooroy Belli Creek Road
    Project:

    Civil Mining & Construction Pty Ltd (CMC) has been awarded the contract to undertake reconstruction works adjacent to 673 and 705 Cooroy Belli Creek Road.

    During work hours the road will be closed with a detour in place. Outside work hours one lane of traffic will be open.

     

    Start date: February 2024
    Duration: Four months, weather and construction conditions permitting
    Related documents:

     

  • There are no capital projects underway at this time.

     

  • There are no capital projects at this time.

  • Location: Schreibers Road
    Project: Work is set to commence to repair damaged infrastructure as a result of the 2022 flood event on Schreibers Road Cooran.
    Start date: 24 September 2023
    Related documents:

    For further information please visit the Disaster Recovery 2022 Floods page

    Location: Coles Creek Road
    Project: Work is set to commence to repair damaged infrastructure as a result of the 2022 flood event on Coles Creek Road Cooran.
    Start date: 19 October 2023
    Related documents:

    For further information please visit the Disaster Recovery 2022 Floods page

  •   Currently no capital projects underway.
  • Location: Cooroy Butter Factory
    Project:

    Noosa Council is replacing the ceiling in the gallery of the Cooroy Butter Facgtory. 

    For the safety of staff and the public the gallery area of the Butter Factory will be closed during replacement work.

    Start date: 19th February 2024
    Duration: 12th April 2024
    Related documents:
    Location: Lake Macdonald Drive
    Project:

    FKG Civil Pty Ltd (FKG) has been awarded the contract to undertake works near 490 Cooroy-Belli Creek Road. The construction will repair landslide damage on the upslope and downslope of the road.

    One lane of traffic will remain open during construction.

    Start date: February 2024
    Duration: Six months, subject to weather and construction conditions
    Related documents:
    Location: Coorory Belli Creek Road
    Project:

    The 2022 flooding event caused damage at several locations on Cooroy-Belli Creek Road. Due to the confined working area, one lane in vicinity of 179 Cooroy-Belli Creek Road must be closed to ensure the safety of motorists and workers.

    Construction will generally be completed between Monday and Friday, 6.30am-5pm.

    For further information please visit the Disaster Recovery 2022 Floods page

    Start date: April 2024
    Duration: Three months, subject to weather and construction conditions
    Related documents:
    Location: Musa Vale Road
    Project:

    Designs and tender documentation are being prepared to reconstruct the road edge on the single-lane section of Musa Vale Road, Cooroy. This section of road was damaged during a landslip caused by the major flooding event in February/March 2022.

    The next steps of the project include:

    • design revision
    • design concept submission for QRA funding approval
    • final design development
    • invitation to tender
    • reconstruction of road asset.

    For further information please visit the Disaster Recovery 2022 Floods page

    Related document:
  • There are no capital projects underway at this time.

  • Location: Cootharaba Road
    Project: Work is set to commence to repair landslide damage to a 40m section of road between 168 and 171 Cootharaba Road, Cootharaba.
    Start date: 5 March 2024
      Two months, subject to weather and construction conditions.
    Related documents:

    For further information please visit the Disaster Recovery 2022 Floods page

    Location: Simpsons Road
    Project: Work is set to commence to repair landslide damage to a 50m long section of road fill embankment adjacent to 37 Simpsons Road.
    Start date: 11 March 2024
      Three months, subject to weather and construction conditions.
    Related documents:

    For further information please visit the Disaster Recovery 2022 Floods page

    Location: Black Pinch road
    Project:

    The 2022 flooding event caused significant damage along Black Pinch Road. The wet weather and landslides caused excessive damage to the road formations and embankments at five separate locations.  

     

    These five sites will be repaired in consecutive order:

    • Site 1 – 325 Black Pinch Road
    • Site 2 – 317 Black Pinch Road
    • Site 3 – 266 Black Pinch Road
    • Site 4 – Adjacent to 241 Black Pinch Road
    • Site 5 – Twin Hills Lookout.

    Please refer to the map showing these locations.

    HEH Civil Pty Ltd (HEH) has been awarded the contract to undertake reconstruction works.

    Reconstruction will include:

    • excavation and disposal of damaged and unsuitable material
    • earthworks
    • bank stabilisation including piling
    • stormwater drainage
    • pavement works.
    State date: Early February 2024
    Duration: Completion expected by early September 2024
    Related document:
  • There are no capital projects underway at this time.

  • There are no capital projects underway at this time.

  • There are no capital projects underway at this time.

     

  • Location: Noosa Biosphere Yurol Trail Upgrade
    Project:

    Noosa Council is upgrading ‘Trail 7’, also known as Yurol Trail, which links Lake Macdonald to Pomona via Yurol State Forest and Tewantin National Park

    The upgrade will improve trail to town connectivity, increase the use of the trails for educational and recreational use, drive tourism and enhance effectiveness as fire breaks throughout the bushland.

    Noosa Council has enlisted the expertise of Sunshine Civil Solutions and Trailworks, while collaborating with National Parks and the Kabi Kabi community on this 14km trail upgrade.

    State date: 15 April 2024
    Duration: 7 weeks, weather and construction conditions permitting
    Related document:
    Location: Botanic Gardens Wedding Chapel
    Project:

    Council contractors will shortly start work on renewal of the wedding chapel in the Botanic Gardens, Lake Macdonald.

    The popular wedding destination has been used for over 20 years, but the structure was removed in 2019 after reaching its end of life.

    The scope of work includes renewal of the courtyard pavement and installation of a new gazebo and arbour walk.

    State date: Early February 2024
    Duration: 6 weeks, weather and construction conditions permitting
    Related document:
  • There are no capital projects underway at this time.

  • Location: Noosa Spit Dog Beach
    Project:

    Sand nourishment works to protect Doggy Beach from further erosion is being planned by Noosa Council. Increasing the volume of sand at Doggy Beach will help reduce erosion caused by the current flow and boat wash.

    Start date: Work will take place between April and the end of September 2024,
    Related document:
    Location: Arkana Drive
    Project:

    Contractors will soon commence manhole work on Akana Drive, Noosa Heads. 

    The work will be undertaken during the day between the hours of 6.30am and 6.30pm.             

    Start date: 23 April 2024
    Duration: 1 day, subject to weather and construction conditions.
    Related document:
  • There are no capital projects underway at this time.

  • Location: Gibson Road
    Project details:

    Contractors will soon commence asphalt resurfacing night works on Gibson Road, Noosaville.

    This work will be undertaken at night between the hours of 6.30pm and 6.30am.

    Start date: 29 April 2024
    Duration: Two nights, subject to weather and construction conditions
    Related document:
    Location: Gympie Terrace & William Street
    Project details:

    Council staff will soon commence road resurfacing work on Gympie Terrace and William Street, Noosaville.

    This work will be undertaken during the day between the hours of 6.30am and 6.30pm.

    Start date: 2 May 2024
    Duration: Two days, subject to weather and construction conditions
    Related document:
    Location: Gympie Terrace Boat Ramp
    Project details:

    Council staff will soon commence work to replace a section of the existing storm water box culvert at the boat ramp on Noosa River Foreshore Boat Ramp carpark. This work needs to proceed as soon as practical to ensure maintenance of the stormwater drainage in this location.

    This work will be undertaken during the day between the hours of 6.30am and 6.30pm.

    Start date: 7 May 2024
    Duration: Three weeks, subject to weather and construction conditions
    Related document:
  • Location: David Low Way
    Project details:

    Contractors will soon commence manhole works on David Low Way, Peregian Beach just past Woodland Drive north bound.

    This work will be undertaken at night between the hours of 6.30pm and 6.30am.

    Start date: 23 April 2024
    Duration: 1 night, subject to weather and construction conditions
    Related document:
    Location: Woodland Drive
    Project details:

    Contractors will soon commence road resurfacing work on Woodland Drive, Peregian Beach.

    This work will be undertaken at night between the hours of 6.30pm and 6.30am.

    Start date: 23 April 2024
    Duration: 1 night, subject to weather and construction conditions
    Related document:
  • Location: Noosa Biosphere Yurol Trail Upgrade
    Project:

    Noosa Council is upgrading ‘Trail 7’, also known as Yurol Trail, which links Lake Macdonald to Pomona via Yurol State Forest and Tewantin National Park

    The upgrade will improve trail to town connectivity, increase the use of the trails for educational and recreational use, drive tourism and enhance effectiveness as fire breaks throughout the bushland.

    Noosa Council has enlisted the expertise of Sunshine Civil Solutions and Trailworks, while collaborating with National Parks and the Kabi Kabi community on this 14km trail upgrade.

    State date: 15 April 2024
    Duration: 7 weeks, weather and construction conditions permitting
    Related document:
  • Location: Ed Webb Park, Belmore Terrace
    Project details:

    Noosa Council is embarking on a project aimed at enhancing safety and accessibility along Belmore Terrace, as an integral component of the Ed Webb Park upgrade. Sunshine Beach.

    This project seeks to unify pathway segments, mitigate trip hazards, and improve safety with the introduction of new pedestrian crossings linking to the Sunshine Beach Surf Club (SBSC)

    Start date: Commence late April 2024 and conclude mid to late June 2024.
    Duration: Three months, subject to weather and contruction conditions.
    Related document:

     

     

     

  • Location: Old Ceylon Road
    Project:

    See the Disaster Recovery page for all the latest information.

    Location: Ridgewood Road
    Related documents:

    For further information please visit the Disaster Recovery 2022 Floods page

     

     

  • Location:

    Butler Street
    Project details:

    Contractors will soon commence manhole night works at the intersection of Butler Street and Irene Street. The work will be undertaken between 6.30pm and 6.30am with traffic control in place.

    Start date: 23 April 2024
    Duration: Completion by 24 April 2024, subject to construction and weather conditions
    Related document:

    Location:

    Griffith Avenue
    Project details:

    Contractors will soon commence kerb and channel work in Griffith Avenue.

    Start date: 20 March 2024
    Duration: Completion by 30 April 2024, subject to construction and weather conditions
    Related document:
  • There are no capital projects underway at this time.

  • There are no capital projects underway at this time.

Community