Skip to Content

Noosa Shire Council

Work in Progress Work in Progress

                                      


Some projects may take a bit longer than anticipated to complete due to extended periods of rain, or contractors being unavailable. Current capital improvement projects are listed here. Other minor capital projects may also be underway.

Choose the suburb or area to see all work being undertaken in that area:

Cooran

Noosaville (includes Doonan)

Cooroy (including Lake Macdonald, Black Mountain & Tinbeerwah)

Peregian Beach (includes Marcus Beach)

Kin Kin

Pomona

Noosa Heads (includes Castaways Beach, Sunshine Beach & Sunrise Beach)

Tewantin (including Boreen Point, Cooroibah, Cootharaba & Noosa North Shore)

 

Shire Wide  
  There are no Shire Wide capital projects underway at this time.
Cooran  
  There are no capital projects underway at this time.
Cooroy  
Location: Black Mountain Road, Black Mountain
Project details:

Work will commence shortly to widen a 200m section of road in front of 378 Black Mountain Road, Black Mountain.

The road widening work involves extensive rock fill, new culverts and new pavement. Access will be reduced to one lane of traffic, with remote traffic signals operating 24 hours a day. Motorists should avoid the area and seek alternate routes if possible.

Start date: 15 May, 2017
Duration: July 2017, weather dependent
Related document:
Kin Kin  
  There are no capital projects underway at this time.
Noosa Heads  
  There are no capital projects underway at this time.
Noosaville  
Location: Gympie Terrace and Thomas Street
Project details:

The existing drainage line between the Noosaville foreshore and along Thomas Street will be replaced in January 2017. Several trees in the foreshore park will be removed and replaced with similar species during the work.

Traffic control will be in place for pedestrian and motorist safety with some kerbside parking bays on Thomas Street closed during the work.

Start date: 26 April 2017
Duration: Completion expected by June 2017, weather dependent
Related documents:
   
Location: Rene Street & Eumundi Noosa Road
Project details:

Contractors have commenced work on resealing Rene Street and a section of Eumundi Noosa Road, Noosaville. The work will be completed at night between 6pm and 6am, Sunday to Thursday.

Every effort will be made to minimise the impact on traffic, however delays of up to 10 minutes can be expected. Motorists should avoid the area if possible.

Start date: 12 June 2017
Duration: 23 June 2017. weather permitting
Related documents:
   
Location:

Lake Weyba Drive

Project details:

Council staff will soon commence work to construct the Lake Weyba Drive bus turn around and repair the stormwater network. This work will see the bus service no longer turning out of Creek Road, instead travelling down Lake Weyba Drive to turn around.

The road will be open to traffic, with traffic control in place. Pedestrian and cycle access will be diverted around the site via Creek Road.

Start date: 29 May 2017
Duration: End of June 2017
Related documents:
Peregian Beach  
Location: Rufous Street, Rufous Laneway and David Low Way
Project details:

Council has awarded the contract for work to begin. Work will include formalising carparks, landscaping, upgrading Rufous Street laneway and pedestrian refuge and crossing work.

Access to all facilities will be maintained with traffic control in place for vehicles and pedestrians.

Start date: 25 January 2017
Duration: Completion by 31 May 2017, weather permitting.
Related documents:
   
Location: David Low Way
Project details:

Contractors will commence preparatory work on the new Peregian Beach Digital Hub this week. To make way for the Digital Hub building, Council will close the existing carpark on David Low Way. The carpark will remain open however, until the finishing touches are complete on the new temporary carpark, next to the tennis club.

The $3M project is funded by Council, with the Queensland Government contributing $1M in grant funding.

Start date: May 2017
Duration: Christmas 2017, weather permitting
Related documents:
Pomona  
  There are no capital projects underway at this time.  
Tewantin  
Location: Kinmond Creek Road, Cootharaba
Project details:

Contractors will shortly commence work to demolish and construct new drainage structures (culverts) on Kinmond Creek Road, between Galloways Lane and Dr Pages Road. This work is required to replace deteriorating culverts, which have resulted in the road being load limited.

The road will be open to traffic under the direction of traffic control for the safety of the public.

Start date: July 2017
Duration: Late 2017
Related documents:
   
Location: Pelican Street, Lake Street, Doonella Street & Parkyn Court
Project details:

Contractors will commence road resealing work on 5 June and will be complete by 15 June 2017, subject to weather conditions. This work will be completed at night between 6pm and 6am, Sunday night to Thursday night.

While the roads will remain open, residents are asked to avoid parking on the street.

Start date: 4 June 2017
Duration: 1 week, weather permitting
Related documents: