Work in Progress

Roadwork ahead sign
Library photo

Some projects/roadworks may take a bit longer than anticipated to complete due to extended periods of rain, or contractors being unavailable. Current capital improvement projects are listed here. Other minor capital projects may also be underway.

View the adopted 2019/2020 Capital Works Program [4.5MB].

Choose the suburb or area to see all work being undertaken in that area:

  • There are no capital projects underway at this time.

  • Location: Black Mountain Road
    Project details:

    $1.2 million of safety improvements on Black Mountain Road will commence shortly. The project is planned to be complete mid-2020, weather permitting.

    The work will include localised widening, new pavement and additional signage.

    Motorists are encouraged to allow more travel time and observe temporary traffic measures to ensure motorist and worker safety.

    Start date: First half of 2020
    Duration: Project to be completed by mid-2020, weather permitting
    Related documents:
  • There are no capital projects underway at this time.

  • There are no capital projects underway at this time.

  • There are no capital projects underway at this time.

  • There are no capital projects underway at this time.

  • Location: Hinterland Playground
    Project:

    Noosa Council is creating a nature-based, all-abilities destination that will inspire the imagination of children and adults alike.

    This iconic destination will encourage more visitors to the hinterland, with the added bonus of creating employment opportunities and helping to boost the local economy.

    Start date: End of 2020
    Duration: Mid 2021
    Related documents: Project news [1.3MB]
    Location: Maple Street Cooroy
    Project:

    To inform the preparation of pavement design options, road pavement testing and sampling will be undertaken on the following roads:

    • Maple Street between Garnet Street and the Corooy Library; and
    • Sea Eagle Drive between Beckmans Road and Shire Drive.

    Stop and go traffic control will be in place temporarily.

    Start date: 2 March 2020
    Duration: 2 days, weather permitting
    Related documents:
  • There are no capital projects underway at this time.

  • There are no capital projects underway at this time.

  • There are no capital projects underway at this time.

  • There are no capital projects underway at this time.

  • There are no capital projects underway at this time.

  • Location: Noosa Heads Surf Club Carpark & Noosa Spit Carpark
    Project:

    Work will shortly commence to demolish the bin enclosure at the Noosa Heads Surf Club carpark and Noosa Spit carpark.

    The contractor will temporarily occupy some car park spaces during work.

    Start date: 2 March 2020
    Duration: 2 weeks
    Related documents: Project news [1.3 MB]
  • Location: Noosa North Shore

    Duration:

    North shore campground plan

    The Noosa North Shore Campground is taking bookings from Friday, 20 December 2019 for the first visitors on 20 January 2020.

    There are over 40 powered sites, nearly 50 unpowered camp sites, a new camp kitchen, beach showers and improved access to the iconic beachfront.

    Start date: April 2019
    Duration: December 2019
    Related document:
  • Location: Sea Eagle Drive
    Project:

    To inform the preparation of pavement design options, road pavement testing and sampling will be undertaken on the following roads:

    • Maple Street between Garnet Street and the Corooy Library; and
    • Sea Eagle Drive between Beckmans Road and Shire Drive. Work on this road has been scheduled outside of school drop off/pick up hours to minimise inconvenience to the community.

    Stop and go traffic control will be in place temporarily.

    Start date: 2 March 2020
    Duration: 2 days, weather permitting
    Related documents:
    Location: Gympie Terrace Stormwater & Corridor Upgrade
    Project details:

    As part of Noosa Council's renewal of vital stormwater infratstructure, culberts and pipes are being replaced at five locations on Gympie Terrace between Robert Street and Ely Park/Pelican Beach Park.

    The project includes road corridor renewal between Cloudsley and Albert streets providing dedicated on-road cycle lanes, pedestrian crossing improvements, and asphalt overlay.

    Start date: February 2020
    Duration: Project to be completed by late June 2020, weather permitting
    Related documents:
  • Location: Peregian Beach Amenities Construction
    Project details:

    Work is set to commence constructing a new public amenities block to replace the existing block adjacent to the surf club building in Peregian.

    During construction a temporary toilet block will be provided immediately south of the existing block.

    Start date: Late July 2019
    Duration: Completion prior to December 2019 holiday period
    Related documents:
    Location: Rufous Street - Stage 3
    Project overview:

    In 2014 Noosa Council purchased the old Peregian Bowls Club site to combine with existing community spaces and create a Rufous Street Community Precinct. Council will progressivley develop the site in stages.

    Following on from the success of the first stages, Council received additional funding from the Federal and State Governments to complete Stage 3 of the Rufous Street Masterplan. Work on Stage 3 has commenced with the civil works. The total project value is $5.2m.

    Start date: Civil works commenced
    Duration: 18 months
    Related documents:
    Location: Rufous Street - water & sewer main upgrades
    Project details:

    Work will commence shortly to upgrade the existing water & sewer main infrastructure at the Rufous Street Community House site.

    Work required includes construction of a new water main and reinstatement of the disturbed work site.

    Start date: May 2019
    Duration: 6 weeks, weather permitting
    Related documents:
  • There are no capital projects underway at this time.

  • Location: Wollomia Way
    Project:

    Work is set to commence on the bus stop at Wollomia Way, Sunrise Beach. The work will include a new concrete boarding platform, incorporating a new bus seat and bin.

    A large tree will be removed to improve public access and protect underground services. As per Councl's policy Tree Management on Public Land, a replacement tree will be planted in a suitable location.

    Start date: Monday, 24 February, 2020
    Related documents:
     
    Location: Orealla Crescent Bridge replacement
    Project:

    Noosa Council is replacing the Orealla Crescent Bridge on David Low Way at Sunrise Beach after regular inspections as part of Council’s ongoing infrastructure maintenance program revealed an increased level of deterioration due to exposure to salt-laden air.

    The bridge renewal project will improve traffic flow and road conditions for all road users, allowing for two traffic lanes, on-road cycle lanes, and a separated off-road shared pathway.

    Closure of David Low Way will be required while the existing bridge is demolished and new bridge constructed. Traffic will be diverted via local roads. Council will provide further information to the local community and motorists about traffic impacts before the start of work

    Start date: Late May 2020
    Duration: About four months, weather permitting 
    Related documents:
  • Location: Pacific Avenue
    Project:

    The Pacific Avenue Sunshine Beach bus stop number 317891 will be upgraded to include:

    • a new concrete boarding platform
    • a new bus shelter
    • a new bicycle hoop
    • rubbish bin facilities; and
    • signage.

    The Queensland Government's Passenger Transport Accessible Infrastructure Program is providing dollar for dollar funding support to Council for these works.

    Start date: 23 January 2020
    Duration: 4 days, weather permitting
    Related documents:
  • There are no capital projects underway at this time.

  • Location: Hilton Terrace
    Project details:

    Work on a $3 million upgrade of Hilton Terrace between the Doonella Bridge and Hilton Esplanade will commence shortly. The project is staged with completion by mid-2020, weather permitting.

    The work will see the construction of a new roundabout at the intersection of Hilton Terrace and Ernest Street and corridor improvements including on-road cycle lane.

    Motorists are encouraged to allow more travel time and to avoid peak hour travel where possible.

    Start date: First half of 2020
    Duration: Project to be completed by mid-2020, weather permitting
    Related documents: